Our experience in the electrical sector gave rise to the initiative to meet the need for a new concept of electrical substations.
Design of high-voltage projects tailored to the needs of businesses. We have created a new concept of custom-designed prefabricated electrical substations.
Factory assembly of the substation and the complete operator station. With all the IT and connectivity infrastructure required in any country.
Every client is different. Their substation format and requirements are tailored to each of their projects.
Designed in transportable, easy-to-assemble modules. Once built, all the control cabinets, switchgear, computers, communication modules and any other required equipment are installed inside.
Customisation and speed This design lets the client choose every option required, with assembly and all testing carried out in the factory, so on-site installation is genuinely fast
Integration with outdoor substations All indoor equipment is pre-connected and the outdoor lines are fitted with IP-67 quick connectors, minimising connections on site and ensuring sealed panels and clean, factory-made wiring.
For a long time, the design of high-voltage projects tailored to the needs of businesses has been one of the tasks of modern engineering. With the expansion of factories and generation plants whose electrical needs require building a substation, it is genuinely one of the most delicate parts of a project. That is why we developed this technology: to simplify the work and design involved in a substation.
This technology consists of carrying out the factory assembly of the substation and the complete operator station, with all the IT and connectivity infrastructure required in any country. Every client is different, and their substation format and requirements are tailored to each of their projects. The substations are fully scalable in size and performance.
The design is based on transportable, easy-to-assemble modules. Once built, all the control cabinets, switchgear, computers, communication modules and any other equipment our client needs are installed inside.
This design lets the client choose every option required, with assembly and all testing carried out in the factory, so on-site installation is genuinely fast.
For integration with outdoor substations, all indoor equipment is pre-connected and the outdoor lines are fitted with IP-67 quick connectors, minimising connections on site.
This type of connection ensures sealed panels and clean, factory-made wiring. PASS or GIS versions can also be offered
Once design begins, one cabinet is planned per bay, plus a general SCADA and overall control cabinet. In the bay cabinets, each element of the bay is wired to terminal blocks on the left-hand side:
For all equipment, spare contacts and positions are brought to the cabinet so that any configuration can be made without changing the external multicore cables.
On the right-hand side of the cabinet, all the low-voltage equipment for that bay is connected:
The central section connects:
Each bay cabinet brings together everything needed for control, signalling and operation.
If there are two bays there will be two cabinets, and so on, which simplifies the design and makes it compatible with every protection scheme and configuration.
Once the operation, control and signalling of each bay are resolved, where there is a double busbar and more than one bay, a cabinet is installed to bring together the common functions:
With the substation configured locally, we move on to the SCADA system for remote control and operation. This requires working hand in hand with the client, as they often have their own models and we must adapt to them and to their communication protocols. Every cabinet is integrated into this SCADA system, which gathers all operation and control signals as well as alarms.
Most substations need two communication systems that can be integrated into the power grid the substation will connect to, so that distance protection can be linked and the high-voltage supply line protected.
The equipment most commonly used is fibre-optic transmission and power line carrier transmission
The substation is now complete and ready to be connected to the grid.
Next comes the client side. As well as having access to substation control from the SCADA cabinet and being able to operate the whole substation manually, an operator station is installed in a separate office. From there all substation parameters, including billing data, can be viewed, and substation components such as the capacitor banks can be operated.
This operator station is integrated into a complete office for controlling, supervising and managing the substation.
In some cases clients have equipment that must be integrated into the substation, such as the system that measures the power and quality of the energy delivered, or the external communications input or internet connection.
The client's equipment is used to control, record and measure power. All indoor and outdoor installations are delivered fully finished, and anything from fire detection and suppression systems to an alarm system can be fitted. Auxiliary services, both AC and DC, are delivered fully finished, with enough modules for future expansion.
Uninterruptible service modules, such as integrated generator sets, are included so that the system is never left without auxiliary services. All substations are fully assembled and connected in the factory. Once assembly is complete, the settings are loaded and the substation and equipment are fully tested, with the client invited to attend.
Once the acceptance tests are complete, the substation is prepared for transport to its final installation site.
The substation is fully connected and tested, so installation at its final location is genuinely fast.
On-site assembly requires a preliminary study, as it depends on weather conditions, regulations and the substation configuration.
Bearing in mind that the most common configuration is a single bay with a transformer and high-voltage line feeders
The control building houses:
All external connections are pre-wired with quick connectors.
One aspect that must be handled individually in each project is the metering system for billing, since the rules differ from one utility to another.
The substation is fully connected and tested, so installation at its final location is genuinely fast.